Enter Planning Information

Explanation

This activity is used to enter planning information for an object. Planning information is entered for objects before they are acquired. You are required to carry out this activity at the time of entering a new object if the object type of the new object being entered is Planned.

Prerequisites

In order to enter planning information for an object, the object status must be either Planned or Investment.

System Effects

As a result of this activity, it would be possible to create a depreciation plan for the object.

Window

Object

Related Window Descriptions

Object/Planning Info

Procedure

  1. Open the Object window and search for the object for which you want to enter planning information.
  2. Click on the Planning Info tab and enter the date on which you plan to acquire the object in the Planned Acquisition Date field. The date entered should be a date within the time period for which the object is valid.
  3. Enter the planned amount in accounting currency to be spent to acquire the object in the Planned Acquisition Value field.
  4. Enter the planned amount in parallel currency in the Planned Acquisition Value in @EU field. (Note: This field is editable only if the company is defined with Transaction Currency as the parallel currency base. If the selected parallel currency base is Accounting Currency, this value is automatically calculated based on relevant currency rate.
  5. Save the information.