Schedule Shop Orders/Operations Automatically or Using
Drag-and-Drop
Explanation
This activity is used to schedule or reschedule shop
order operations using the Advanced Planning Board (APB), either manually or
automatically. This can be performed on
sites which have been set up to use the APB. Scheduling can be carried out either automatically or
using the drag-and-drop of operations. This activity can be used to move individual
shop order operations or the entire Dynamic Order Processing (DOP) structures at a
time.
Prerequisites
- The shop orders which are to be scheduled must
have been loaded to the Advanced Planning Board.
- The shop orders which are to be rescheduled using
drag-and-drop must have been scheduled automatically.
- The shop order or structure must have at least one operation in
Scheduled or Released state within the APB.
- The operations may not be in Partially Reported or Reported
state.
System Effects
N/A
Window
Advanced Planning Board
Related Window Descriptions
Advanced Planning Board
Procedure
Automatic scheduling:
- In the
Activities tab of the Advanced Planning Board, select the shop order for which you want to perform this
activity.
- Drag the order into the object table area of the
Gantt chart while pressing the Shift key. It will be placed in
the object table area with its operations already expanded.
- Select the shop order, right-click and then click
Scheduling. This will open the Change Schedule window.
- Select the required scheduling options in the
Scheduling action(s), Schedule Mode and Resource Assignments
areas.
- Click OK. The order will be scheduled
according to the options selected in step 4. You can see this in the Gantt
chart.
Rescheduling operations/DOP structures using
drag-and-drop:
- In the
Activities tab of the Advanced Planning Board, select the shop order for which you want to perform this
activity.
- Drag the order into the object table area of the
Gantt chart while pressing the Shift key. It will be placed in
the object table area with its operations already expanded.
- Select an operation, right-click and drag it to
the left or right and release the mouse button. You can even move the entire shop
order, multiple shop orders and DOP structures in this manner as well.