Serial Structure Information/Additional Serial Info/Supplier Warranty

[About Warranty] [To Manage Serialized Configuration]

Usage

Use this tab to view or update a supplier warranty that is connected to the selected serial. If warranty dates, i.e., as shown in the Valid From and Valid To fields, have not been calculated, right-click and then click Calculate Dates to perform the calculation manually. Furthermore, if needed, you can directly enter or modify the minimum and maximum validity periods for the warranty condition in this tab. Note that the Calculate Dates option can only be performed on the warranty conditions that have a valid Time Unit connected to it.

Supplier warranties are created in IFS Supply Chain. For more information, refer to the activity Enter and maintain Supplier Warranties.

Activity Diagrams

Define Serial Structure

Activities

Calculate Warranty Dates