Handle Changes
Explanation
When setting a new baseline, the
values for baseline cost and hours are set to be identical to the budget cost
and hours. Similarly, the baseline dates are set to be identical to the early
start and finish dates. However it is common that the planned values or early
dates will continue to be updated even though a baseline has been set, and
changed or new activities will be marked as changed. Perform this activity to
find which activities have been changed after the last baseline revision has
been created, in order to assess if a new baseline needs to be set or if there
are other consequences of the changes.
Subsequently, when setting a new
baseline, the new baseline revision will be shown on all such activities which
had been changed or added. This field gives information about which baseline
revision the activity first appears with its current baseline values or baseline
dates.
Prerequisites
- The project must be in the Approved
or Started status.
System Effects
- The Activity Changed checkbox will be automatically
selected if an activity is added or changed after a baseline has been set.
- When setting a new baseline, all activities that have been
added or changed since the last baseline revision was set, will receive the
new baseline revision number as its value in the Set in
Baseline field. The Activity Changed checkbox will than be
cleared.
Window
Project Navigator
Activity
Activities
Related Window Descriptions
Project Navigator/Activity List
Project Navigator/Activity
Activity
Activities
Procedure
When changing or adding activities:
- Make a change so that a value
for an activity planned cost or hours is changed. Alternatively, change the
activity early start or finish date.
- Add a new activity.
- Observe that the Activity Changed
checkbox is now selected on the changed or new activities.
Note:
If no
baseline revision has yet been set, all activities will have
the Activity Changed
checkbox selected.
When setting a new baseline
revision:
- For all activities which had
the Activity Changed
checkbox selected, the new baseline revision value is shown in the Set in
Baseline field.
- The Activity Changed
checkbox is cleared for all the project activities.