Usage
Use this dialog box to retrieve the demands for the parts
on the line, to be used in takt time calculations. Based on the input demand
selection date range, the demands are retrieved into a local snapshot of demands,
from one or more of the sources that you have selected.
The available options are:
- Customer Order Released customer orders that
have not been picked or shipped as yet
- Customer Schedule Planned Demand schedule data for
released schedules
- Production Schedule (component demands)
Component
quantities required from unreceived production schedules
- MS/MRP Master Schedule Level 1 and MRP planned
receipts
You cannot select MS/MRP along with any of the other sources,
as the MS/MRP snapshot typically includes these demands already.
Activity Diagrams
Production line
management
Activities
Retrieve production line
demands