Purpose: The purpose of these initial exercises is that the instructor will use them for demonstrating the basic functionality in Manufacturing Standard, which entails:
Performing Engineering Transfer
Creating Product Structure
Creating Recipe Structure
Creating Plan Structure
Creating Routing
Calculate Lead time
Creating New Structure/Routing Revision
Creating New Part Revision
Creating Structure/Routing Alternative
IMPORTANT |
These initial exercises are intended for
instructor use. If you are a student, it is extremely important that you set up and work within your own site to maintain your data integrity. If you work within any other site, you will compromise your own exercise data as well as the data of other students. Predictable exercise results require that your data be isolated in your own site. |
Purpose: The purpose of this exercise is to familiarize you with the basic functionality of transferring parts and structures from IFS Engineering.
Prerequisites: Manufactured and purchase engineering parts must exist.
Windows:
Engineering Revision Transfers
Product Structure
Note: Engineering parts are site independent.
Note: Once templates are created in the Part Transfer Template window, they are automatically connected to the correct part type, and the information appears in the columns listed above.
Component Part No | Component Part Description |
20–110 | Engine Block |
20–120 | Cylinder Head |
20–130 | Electric System |
20–140 | Cooling System |
Purpose: The purpose of this exercise is to introduce you to the basic functionality for creating a product structure.
Prerequisites: Manufactured and purchased inventory parts must exist.
Note: If you have not yet already done so, copy Inventory Part 20–250 on Site 1 to IE20–250, also on Site 1.
Windows:
Product Structure
Line Item No | Component Part | Qty per Assembly |
1 | 20–350 | 1 |
2 | 20–351 | 1 |
3 | 20–352 | 1 |
Purpose: The purpose of this exercise is to introduce you to the basic functionality for creating a recipe structure
Prerequisites: Manufactured recipe and purchased inventory parts
Note: If you have not yet already done so, copy Inventory Part 80–400 on Site 1 to IE80–400, also on Site 1.
Windows:
Recipe Structure
Line Item No | Component Part | Qty in Display Weight |
1 | 80–501 | 76.0 |
2 | 80–502 | 64.0 |
3 | 80–505 | 44.0 |
4 | 80–510 | 16.0 |
5 | 80–506 | –0.2 |
Purpose: The purpose of this exercise is to introduce you to the basic functionality for creating a planning structure.
Prerequisites: Manufactured and purchase inventory parts must exist.
Note: If you have not yet already done so, copy Inventory Part 20–000 on Site 1 to IE20–000, also on Site 1.
Windows:
Planning Structure
Line Item No | Component Part | Qty per Assembly (Percentage) |
1 | 20–101 | 0.4 |
2 | 20–102 | 0.7 |
Purpose: The purpose of this exercise is to introduce you to the basic functionality for creating routing and to enter some of the data for an operation.
Prerequisites: A structure must exist for the part.
Windows:
Routing
Operation No. | Description | Work Center | Machine Setup time | Machine Run Factor | Labor Class | Labor Setup Time | Labor Run Factor | Factor Unit |
10 | Assemble Part | 300 | 0 | 0.2 | 1 | 0 | 0.2 | Hours/Unit |
Purpose: The purpose of this exercise is to familiarize you with the basic functionality for calculating the manufacturing and cumulative lead time.
Prerequisites: A structure must exist with a routing connected as described above.
Windows:
Lead time Calculation
Cumulative Lead time Calculation
Inventory Part
Note: IFS Racing has entered its manufactured parts with their structures and routings. Your next objective is to update the calculated lead time for the parts.
Note: The calculate is a batch job, so you must wait for the job to run.
Component Part | Purchase Lead Time |
20–350 | 20 |
20–352 | 5 |
Note: The calculate is a batch job, so you must wait for the job to run.
Purpose: The purpose of this exercise is to familiarize you with the basic functionality for creating new revisions.
Prerequisites: A structure with a routing connected must exist.
Windows:
Product Structure
Routing
Note: The same procedure applies to routings.
Purpose: The purpose of this exercise is to familiarize you with the basic functionality for part revisions.
Prerequisites: An inventory part must exist.
Windows:
Part Revision
Part Revisions
Part No. | Part Description | Phase In | Phase Out |
IE20–250 | Fuel system | Current date + 30 days | Current date + 60 days |
Purpose: The purpose of this exercise is to familiarize you with the basic functionality for creating new alternatives.
Prerequisites: A structure/routing and a purchase part must exist.
Windows:
Product Structure
Routing
Alternative | Alternative Description |
1 | Purchase alternative |
Note: The same procedure applies to recipe structure and routings.
Line Item No | Component Part | Qty per Assembly |
1 | 20–350 | 1 |
2 | 20–353 | 1 |
3 | 20–352 | 1 |